October 2021

Liquidated Damages - the Effect of Contract Termination

Andrew Harvey Marketing Consultant

In Triple Point Technology, Inc v. PTT Public Company Ltd [2021] UKSC 2 (16 July 2021) the UK Supreme Court provided a reminder of the effect of termination of a contract on a liquidated damages provision. If the provision is silent on the consequences of termination of the contract:

  • Liquidated damages will cease to accrue on termination, but those accrued as at the date of termination will survive.
  • Following termination, a claim for damages for breach of contract under general English law principles should be pursued.

The parties to a contract should therefore consider whether this is the outcome they wish to apply or whether language should be included to allow recovery of liquidated sums after termination, thus potentially avoiding the task of proving loss in a general damages claim.

Photo by Farzad Nazifi on Unsplash

If you have any questions, please contact Paul de Cordova, or your usual Jurit contact.

Andrew Harvey Marketing Consultant - +44 (0) 20 7846 2370 andrew.harvey@jurit.com
  • LinkedIn
  • Twitter
  • Facebook

Please note this paper is intended to provide general information and knowledge about legal developments and topics which may be of interest to readers. It is not a comprehensive analysis of law nor does it provide specific legal advice. Advice on the specific circumstances of a matter should be sought.

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.